History in the Making: SDS Starts Water Delivery [April 28]

Here’s the release from Colorado Springs Utilities:

One of the largest water infrastructure projects completed in the U.S. this century started delivering water today to homes and businesses in Colorado Springs, Colo. The commencement of the Southern Delivery System (SDS) culminates decades of planning and nearly six years of construction.

See video.

“The Southern Delivery System is a critical water project that will enable the continued quality of life southern Coloradans enjoy. The water provided through SDS means future economic growth for our community,” said Jerry Forte, Chief Executive Officer of Colorado Springs Utilities.

Not only does SDS meet the immediate and future water needs of Colorado Springs and its project partners Fountain, Security and Pueblo West through 2040, it also increases system reliability should other parts of the water system need maintenance or repairs. The project will also help provide drought protection, a significant benefit in the arid west.

Construction started in 2010 and concluded in 2016. Originally forecast to cost just under $1 billion, SDS is started on time and more than $160 million under budget costing $825 million.

“On time and under budget are words rarely used to describe large infrastructure projects,” said John Fredell, SDS Program Director. “We adopted a philosophy that ‘these are ratepayer dollars’ and managed the project with exceptional rigor. It was the responsible approach to spending hundreds of millions of dollars of public money.”

Components of SDS
SDS is a regional project that includes 50 miles of pipeline, three raw water pump stations, a water treatment plant (pictured above), and a finished water pump station. It will be capable, in its first phase, of delivering 50 million gallons of water per day and serving residents and businesses through 2040.

Key permits and approvals for SDS required $50 million in mitigation payments to the Fountain Creek Watershed District, funding for sediment control, habitat improvements and other environmental mitigation measures. Additionally, Colorado Springs and Pueblo County, just this week, both approved an intergovernmental agreement requiring Colorado Springs to invest $460 million over 20 years to improve the management of stormwater that makes its way into Fountain Creek.

Early on in the project, SDS program leaders agreed to spend at least 30 percent of construction dollars on local contractors. More than $585 million, or about 70 percent of the SDS budget, went to Colorado businesses.

“SDS is one of the most important projects many of us will ever work on,” said Forte. “This is a legacy project – one that benefits so many people today, tomorrow and for generations to come. This is an amazing day for our organization and for southern Colorado.”

The new north outlet works at Pueblo Dam -- Photo/MWH Global
The new north outlet works at Pueblo Dam — Photo/MWH Global

From the Associated Press via The Aurora Sentinel:

Water has begun flowing into Colorado Springs through a new 50-mile pipeline from the Arkansas River.

The city says the $825 million Southern Delivery System started operating Thursday.

The system is designed to handle growth in the state’s second-largest city until 2040 and provide a backup for its current aging system.

Pueblo West, Fountain and Security also get water from the pipeline.

The project includes modifications to Pueblo Dam on the Arkansas River, three pumping stations and a treatment plant.

Separately, Colorado Springs had to commit $460 million to reduce sediment in Fountain Creek. The sediment harms downstream communities in Pueblo County, and the county threatened to revoke a required permit for the pipeline if the issue wasn’t addressed.

SDS: “It has been a lot to get this Pueblo County agreement out of the way and taken care of successfully” — John Fredell

Southern Delivery System construction celebration August 19, 2011 via The Pueblo Chieftain
Southern Delivery System construction celebration August 19, 2011 via The Pueblo Chieftain

From The Colorado Springs Gazette (Billie Stanton Anleu):

The $825 million Southern Delivery System’s treatment plant was ready to serve drinking water Wednesday, as a project 20 years in the making finally made its debut.

The distribution system will be turned on Thursday to deliver water to Colorado Springs, Security and Fountain, and water will begin reaching those customers Friday. The SDS already supplies water to Pueblo West, which needed early assistance after a major water pipe in its system broke.

“Things are going great, just like we’ve always planned,” SDS Project Manager John Fredell said Wednesday. “We’ve worked on a lot of these issues a long time to get ready.”

The project hit a snag last year when Pueblo County, which had issued the essential SDS 1041 permit, began seriously pressuring Colorado Springs leaders.

The county insisted on more city stormwater projects to protect downstream residents from excessive flows, sediment buildup and water quality degradation in Fountain Creek.

The City Council signed an intergovernmental agreement April 20. It promises, among other things, to spend $460 million on 71 mutually beneficial stormwater projects over the next 20 years, with Colorado Springs Utilities guaranteeing any funds the city can’t provide.

Pueblo County commissioners approved that pact Monday, enabling SDS to kick off its operations on Wednesday, the target date set years ago.

“It has been a lot to get this Pueblo County agreement out of the way and taken care of successfully,” Fredell acknowledged. “But I really did not fear that it wasn’t going to happen. It was just a matter of timing.”

Colorado Springs Mayor John Suthers has spent much of his first year in office negotiating with Pueblo County and with the U.S. Environmental Protection Agency on the city’s long-time stormwater program deficiencies.

Dan Higgins, chief water services officer for Utilities, called it “a great day.”

“I look back at all the things we’ve seen our team experience,” Higgins said. “We’ve been through so much together. It’s just a fantastic experience for everybody that’s been involved.”

As usual, Fredell credits his project team for a job well done.

“I’m telling you, without all these great people putting out every ounce of energy they have, we couldn’t have done it,” Fredell said. “And to me that’s just so cool, to bring all these people together and they’re all pulling in the same direction.

“To me, that’s the coolest thing. I feel like the whole team, we have stronger friendships now than when we started. How many teams can say that? To me, that’s absolutely incredible.”

The project team determined in July 2009 that the SDS would start operating in April 2016.

“I’ll feel better Friday,” admitted Kim Mutchler, who has worked on SDS for Utilities’ government and corporate affairs team. “There’s a lot going on between now and then.

“I’m happy for these guys who have been on this project for so long. It’s just exciting to see (Utilities) board members and previous council members. We had a couple out there yesterday seeing (the plant) for the first time. It’s nice to see them excited.”

From The Pueblo Chieftain (Chris Woodka):

The need for Colorado Springs to control stormwater on Fountain Creek was always tied to the Southern Delivery System, and the new agreement with Pueblo County is designed to cement the relationship.

During the permitting process for SDS, stormwater control was mentioned in both the Bureau of Reclamation environmental impact statement and Pueblo County’s 1041 permit.

Ever since Colorado Springs City Council abolished its stormwater enterprise in 2009, the city engaged in political gymnastics to assure Pueblo County it was doing enough.

Monday’s completion of an intergovernmental agreement should represent an end to political bickering over stormwater, because it spells out very clearly what has to be done over the next 20 years.

Commissioners were quick to point out Monday that the items contained in the agreement are not the only things Colorado Springs must do in relation to SDS under the 1041 permit. But they have to do these things:

Fund stormwater control with at least $460 million over the next 20 years.

The funding will go toward 71 projects on a set schedule that can be adjusted only if both parties agree.

The amount of funding steps up from at least $20 million per year in the first five years to at least $26 million per year in the last five.

While the money can be matched with other funds, Colorado Springs must come up with the minimum amount, but the sources are not specified. Annual reports are required.

Colorado Springs also is required to resolve any conflicts with the IGA that might result from action by the Department of Justice, EPA and Colorado Department of Public Health and Environment over the city’s failure to meet the terms of its municipal stormwater permit from 2013-15.

A provision of the IGA requires Colorado Springs to notify Pueblo County of any variance to its drainage criteria manual. The failure to apply the document to new development was among deficiencies identified by the EPA in its audit of Colorado Springs’ stormwater permit.

Regional cooperation on Fountain Creek.

The IGA triggers the first two payments of $10 million each that were negotiated under the 1041 permit. Five annual payments of $10 million are required. The money must be used for a dam, detention ponds or other flood control structures that protect Pueblo from flows on Fountain Creek that have increased because of growth in Colorado Springs and El Paso County.

The first payment is actually $9,578,817, because of credits for payments already made and an “index” fee, which amounts to interest payments. It will come within 30 days.

The second $10 million payment will be made Jan. 15.

The payments go to the Fountain Creek Watershed Flood Control and Greenway District, which was created by the state Legislature to improve Fountain Creek.

Formed in 2009, the district grew out of discussions between the two counties. Pueblo County Commissioner Sal Pace sponsored the legislation when he served as a state representative.

The IGA also provides $125,000 to the district, which will be used in part to help fund a state study of a dam or detention ponds on Fountain Creek. The money is in addition to the $50 million required under the 1041 permit. The Fountain Creek board will determine exactly how the money is spent.

Both Pueblo County and Colorado Springs agree to work with other governments to find a permanent source of funding for the Fountain Creek district.

Colorado Springs also will pay $3 million over three years to the city of Pueblo for repairs to levees, dredging and removal of debris or vegetation in Fountain Creek.

Pueblo is required to match the money, but can use about $1.8 million that Pueblo County is still holding from $2.2 million Colorado Springs was made to pay for dredging in Pueblo. Some of the money was spent on demonstration projects.

The agreement also specifies that any disputes will be handled in the same way as disagreements in the 1041 permit. If not successful, legal action over the IGA would be handled in Pueblo District Court.

Southern Delivery System to be turned on today after decades — The Pueblo Chieftain

Southern Delivery System map via Colorado Springs Utilities
Southern Delivery System map via Colorado Springs Utilities

From The Pueblo Chieftain (Chris Woodka):

Colorado Springs Utilities plans to begin using the Southern Delivery System today, more than seven years after getting the green light from Pueblo County and the Bureau of Reclamation to build it. “We plan on 5 million gallons a day initially, but we may go less. It depends on how we use it,” said John Fredell, SDS project director. “On Thursday, the water we pump will be turned into our system.”

SDS will be able to operate after an agreement was reached on Fountain Creek stormwater control on issues not explicitly covered in Pueblo County’s 1041 permit. The new agreement contains funding benchmarks that were not originally in place.

Over the next 40 years, the amount of water pumped through SDS could increase to as much as 75 million gallons a day. Another 18 million gallons a day could be pumped to Pueblo West, which through a special agreement already is using SDS for its water supply.

The treatment plant as built can treat up to 50 million gallons per day, but eventually could be expanded to treat up to 100 million gallons per day.

As part of SDS, the city of Fountain can receive more of its water through the Fountain Valley Conduit, a line built from Pueblo Dam in the early 1980s as part of the Fryingpan-Arkansas Project.

The other partner in SDS is Security Water and Sanitation, which serves an unincorporated area south of Colorado Springs and has an immediate need for a new water source because of well contamination.

Construction on the $825 million project began in 2011, one year after the Bureau of Reclamation approved the final contract for the use of Lake Pueblo as part of the project. In 2009, Reclamation issued a record of decision that allowed the project to be built.

Also in 2009, Pueblo County commissioners approved a land-use permit under the 1974 HB1041, which lets cities or counties regulate projects that cross their boundaries.

SDS includes a new connection built at Pueblo Dam, three pump stations, a water treatment plant and a treated water pump station. The North Outlet Works, Juniper Pump Station just northeast of Pueblo Dam and about 17 miles of buried 66inch diameter pipeline are the features of SDS in Pueblo County.

The project grew out of water resources plans that began in the late 1980s, when Colorado Springs purchased controlling interest in the Colorado Canal system in Crowley County.

In order to use the water, as well as provide redundancy for its other sources of water, Colorado Springs developed a Water Resource Plan in 1996. That plan identified other alternatives to bring water to Colorado Springs, including a route from a new reservoir at Buena Vista, a Fremont County pipeline and a line from Crowley County.

By the early 2000s, the Buena Vista reservoir was eliminated by environmental protests, and Utilities ruled out Crowley County because of the expense of overcoming water quality issues. By 2008, Fremont County and Pueblo Dam were being seriously considered.

The Pueblo Dam option was chosen in Reclamation’s record of decision as the route.

In the second phase of SDS, which is anticipated to begin between 2020-25, two reservoirs would be built on Williams Creek east of Fountain. The upper reservoir would be terminal storage for the pipeline from Pueblo Dam, while the lower one would regulate return flows from Colorado Springs’ wastewater treatment plant into Fountain Creek.

SDS is designed to serve a population of 900,000, about twice the current number living in Colorado Springs.

The 1996 water resources plan came at a time when Colorado Springs’ population had increased from 70,000 in 1960 to 330,000 in 1996. Utilities already is working on a 50-year plan to meet its future water resource needs.

More Coyote Gulch Southern Delivery System coverage here and here.

Pueblo County OKs stormwater deal with Colorado Springs — The Pueblo Chieftain

From The Pueblo Chieftain (Anthony A. Mestas):

It was called a historic day for Pueblo County and Colorado Springs.

Pueblo County commissioners approved an agreement over the Southern Delivery System with its Front Range neighbors to the north during a meeting at the courthouse.

The agreement is a clarification of the rules and responsibilities with regards of one of the issues with a 1041 permit dealing with the SDS project, mainly how to control stormwater, flooding and sediment transports along Fountain Creek.

“We think it is historic,” Commissioner Terry Hart said. “This has been a growing process. It’s been a learning process as the growth of Colorado Springs has impacted more and more our downstream community.”

In the agreement, Colorado Springs would pay more than $605 million to cover environmental damage for SDS should the intergovernmental agreement with Pueblo County be approved.

The proposed deal includes a guarantee to spend at least $460 million over the next 20 years to repair and build storm water structures in Colorado Springs in a way that benefits downstream communities, particularly the city of Pueblo.

Colorado Springs approved the agreement last week.

“We are thrilled that we reached this point,” Hart said.

“A lot of folks see this as an ending to a process and it’s just the opposite. It’s just the beginning. It’s a more cooperative approach between the two communities.”

Cartoon via The Pueblo Chieftain
Cartoon via The Pueblo Chieftain

#Colorado Springs, three other cities one vote away from [improved] water-supply security — The Colorado Springs Gazette

Here’s an in depth look at the new Southern Delivery System which is about to go online from Billie Stanton Anleu writing in The Colorado Springs Gazette. Click through and read the whole article and to check out the photos. Here’s an excerpt:

The launch of the long-awaited SDS hinges on a vote by Pueblo County commissioners Monday to approve a stormwater deal with Colorado Springs, thus freeing the SDS 1041 permit the commissioners granted in 2009.

The start of the SDS will culminate 20 years of planning, years of quarreling between Pueblo County and Colorado Springs, and six years of building 53 miles of huge pipelines, three pump stations and a 100-acre water treatment plant.

The $825 million project will pump 5 million gallons of water a day – and up to 50 million when needed – to Colorado Springs, Pueblo West, Fountain and Security.

The project was a figment in 1996, when the Colorado Springs City Council approved a Water Resource Plan to explore how best to sate the thirst of a rapidly growing population.

In July 2009, the council approved the SDS as the best of seven alternatives – just as the recession struck. So the project was used as “our own stimulus,” says SDS Program Director John Fredell.

Workshops in Pueblo, El Paso and Fremont counties showed contractors how to work with Colorado Springs Utilities.

The only Colorado company that could build the huge pipes, of 66- and 90-inch diameter, competed against out-of-state bidders but got more than $100 million in business with the SDS.

And that firm wasn’t alone. A contract goal said 30 percent of business should go to Colorado firms. Contractors who failed to meet that threshold were penalized. And the goal was exceeded, Fredell said.

More than 430 Colorado companies have worked on the SDS. Of the $711 million spent through December, $585 million worth of work has stayed in Colorado – about $287 million in El Paso County, $75 million in Pueblo County and $222 million elsewhere in the state.

Meanwhile, what Fredell calls the toughest part of the whole project ensued.

His team spent five years creating a 3,000-page Environmental Impact Statement and obtaining the 1041 permit from Pueblo County. It also had to get about 350 other permits, 200 of them major. Even the Federal Aviation Administration had to OK the plan, as the water treatment plant off of Colorado 94 is in the Colorado Springs Airport flight line.

When construction commenced in 2010, the first challenge was connecting to the Pueblo Dam.

Water flowing from the dam’s North Outlet Works into the Arkansas River was rechanneled so the square outlet channel could get a round pipe fitting to connect to the liner pipe through the dam to the river outlet, said Dan Higgins, chief water services officer for Utilities.

A 0.3-mile pipe segment also was installed from the valve house to the Juniper Pump Station, to link Pueblo West to the SDS and carry water for the other users. Juniper is the first of three pump stations needed to move the water 53 miles uphill. El Paso County became home to the Williams Creek and Bradley pump stations.

The water is being moved through massive pipes buried 85 feet beneath Interstate 25, Fountain Creek and two sets of railroad tracks. One mile of that stretch is a tunnel about 20 miles south of downtown Colorado Springs.

The destination? The Edward W. Bailey Water Treatment Plant, named for “one of the real geniuses of the 1996 water master plan,” said City Council President Merv Bennett.

That 100-acre plant can purify 50 million gallons of water a day, which then goes through a pump station for treated water and more pipelines to reach customers.

The Bailey plant’s developed area could contain 77 football fields, said Kim Mutchler, of Utilities government and corporate affairs.

Utilities water customers are paying for this project. But they’re paying a lot less than projected, as cost-cutting measures shaved the project’s predicted $985 million price tag.

In 2009, Utilities predicted seven consecutive years of 12 percent water rate increases, followed by two years of 4 percent hikes. Instead, rates rose 12 percent in 2011 and 2012 and 10 percent in 2013 and 2014.

The project is needed for many reasons, community leaders agree.

Because Colorado’s second-biggest city isn’t near a major river, it has relied on water brought over the Continental Divide. But those pipelines are nearly 50 years old.

With another 350,000 residents expected to move to El Paso County over the next 30 years – while industry and businesses need water, too – the Southern Delivery System is seen as a move to secure the city’s future.

If water demand increases, SDS will add two reservoirs, increase the raw water delivery capacity, and expand the water treatment plant and pump stations to deliver more than 100 million gallons a day – double the maximum available starting Wednesday.

Southern Delivery System map via Colorado Springs Utilities
Southern Delivery System map via Colorado Springs Utilities

Pueblo County’s stormwater control agreement with Colorado Springs fine-tuned — The Pueblo Chieftain

Last section of pipe for Southern Delivery System photo via The Colorado Springs Gazette
Last section of pipe for Southern Delivery System photo via The Colorado Springs Gazette

From The Pueblo Chieftain (Chris Woodka):

The final agreement between Pueblo County and Colorado Springs on Fountain Creek is fine-tuned to reflect some of the concerns expressed earlier this week in public hearings.

“After we got feedback, there were a few minor adjustments,” Pueblo County Commissioner Terry Hart told the Fountain Creek Watershed Flood Control and Greenway District Friday. “In general, citizens have liked the agreement. It gives both communities the chance to work together. The second thing we heard was: ‘Let’s work together and start doing projects.’ ”

Pueblo County commissioners are scheduled to vote on the agreement Monday, capping a year of negotiations with Colorado Springs over the issue of stormwater control and the 1041 permit for the Southern Delivery System pipeline to deliver water from Lake Pueblo to Springs.

Colorado Springs City Council approved the deal on Wednesday, with the promise to spend at least $460 million on stormwater control in the city over the next 20 years.

The agreement also triggers the $50 million in payments over the next five years for the Fountain Creek district, provides $125,000 in funds for the district’s general fund this year and adds $3 million for dredging and debris removal in Pueblo over the next three years.

“We have two projects underway right now,” Colorado Springs Councilman Andy Pico told the Fountain Creek board.

The agreement now recognizes that Colorado Springs’ obligations on Fountain Creek will continue for the lifetime of the project. Hart explained that the agreement now under consideration simply defines specific actions that will occur in the next 20 years. The 1041 agreement includes stormwater language that will continue to apply.

Two other tweaks in the language clarified that the $20 million provided to the Fountain Creek district by Jan. 15 would be used to fund dams on Fountain Creek and that vegetation as well as sediment could be removed from Fountain Creek.

The district board also learned that an additional $10 million in federal funds over the next five years could be available, although the grant from the Natural Resources Conservation Service is only in the exploratory stages.

It also pondered ways to permanently fund the district — a new commitment shared by Pueblo County and Colorado Springs in the proposed agreement. The members generally agreed a straight pro rata method based on population would be the fairest way. A formal vote could come in May.

Until the district decides to use its statutory power for a mill levy, it will rely on voluntary contributions from member governments, which include Pueblo and El Paso counties, Pueblo, Colorado Springs, Fountain and other incorporated cities in El Paso County.

SDS: #Colorado Springs councillors OK stormwater agreement with Pueblo County

Southern Delivery System map via Colorado Springs Utilities
Southern Delivery System map via Colorado Springs Utilities

From The Colorado Springs Gazette (Billie Stanton Anleu):

The City Council committed Colorado Springs on Wednesday to spend more than $460 million over 20 years on a stormwater projects pact with Pueblo County.

The intergovernmental agreement, negotiated chiefly by Mayor John Suthers, is expected to resolve Fountain Creek stormwater problems for downstream residents and avert lawsuits threatened by the U.S. Environmental Protection Agency through the Department of Justice and by Pueblo County.

Further, the accord would allow Colorado Springs Utilities’ Southern Delivery System to start pumping water as scheduled on April 27.

Pueblo County officials threatened to rescind that $825 million project’s 1041 permit, which they issued in April 2009, if the city didn’t ante up enough guaranteed funding for stormwater projects.

The deal now hinges on a vote by Pueblo County’s three commissioners, set for 9 a.m. Monday.

Any delay of the SDS would reduce the worth of warrants on equipment and work while leaving four partner communities – Colorado Springs, Pueblo West, Fountain and Security – without the water deliveries they expect.

The council, meeting in special session Wednesday, didn’t hesitate to approve the pact. Only Councilwoman Helen Collins, a steadfast foe of government spending, dissented in the 8-1 vote.

The agreement calls for 71 stormwater projects to be completed by 2035. Engineers for Pueblo County and Colorado Springs chose the projects and will review them each year to allow for fluctuating priorities.

The money will be spent in five-year increments, at a rate of $100 million the first five years followed by $110 million, $120 million and $130 million. Any private developers’ projects or other efforts would be in addition to the promised amounts.

If the projects aren’t completed in time, the accord will be extended five years. And if Colorado Springs can’t come up with the money required, the city-owned Utilities will have to do so.

The agreement was tweaked slightly Wednesday, on request of the Pueblo County commissioners, to increase one miscalculated payment to a water district by $332, to add the word “dam” to references to a study of water-control options, and to add “and vegetation” to a clause about removing debris from Pueblo’s city levees. A clause was added to note that after the agreement expires, both sides agree to coordinate and cooperate with one another, as they always will be upstream-downstream neighbors.

“This is basically an investment in this city,” said water attorney David Robbins, a consulting lawyer for the council. “The stormwater facilities would have ultimately had to be built anyway. They benefit your citizens, not just the people downstream.”

Asked about the option for a dam, Robbins said, “It has been studied, studied again, and another study may add to our knowledge, but doesn’t require this city to contribute any more money. The dam would require moving two railroads and an interstate highway. Just the facility relocation costs make it quite expensive.”

Colorado Springs has failed to properly enforce drainage regulations, conduct adequate inspections, require enough infrastructure from developers or properly maintain and operate its stormwater controls, the EPA found during inspections in August.

The downstream victim has been Pueblo County, which saw Fountain Creek sediment increase at least 278-fold since the Waldo Canyon fire in 2012, degrading water quality and pushing water levels higher, Wright Water Engineers Inc. found during a study for the county last year.

Sediment increased from 90 to 25,075 tons a year, while water yields rose from 2,500 to 4,822 acre-feet, the engineers found.

As Colorado Springs development sprawls, the amount of impermeable pavement grows. So the city also is beefing up its long-underfunded Stormwater Division, increasing the staff of 28 to 58 full-time employees, mostly inspectors, and more than doubling the $3 million budget for compliance to about $7.1 million.

The city and Utilities negotiated for nearly a year with Pueblo County, as Colorado Springs has beefed up its stormwater program to fix the problems and fend off the threats of lawsuits.

From The Pueblo Chieftain (Chris Woodka):

The Pueblo Board of Water Works would like to see up-front bonding and longer term for an intergovernmental agreement between Pueblo County and Colorado Springs.

Still, it’s probably the best deal possible, the board agreed during comments on the proposed deal at Tuesday’s monthly meeting.

In February, the board provided its input with a resolution recommending certain actions to Pueblo County commissioners.

Colorado Springs City Council approved the deal Wednesday, while Pueblo County commissioners will meet on it Monday. It provides $460 million for stormwater projects over the next 20 years, triggers $50 million in payments over five years for Fountain Creek dams and adds $3 million to help dredge and maintain levees in Pueblo.

“One of the things we encouraged Colorado Springs to do was bond the projects up front,” said Nick Gradisar, president of the water board. “It would be to everyone’s advantage to do the projects sooner rather than later.”

Board member Tom Autobee said the agreement is comprehensive, but was uncertain about the 20-year timeline for improvements.

“What I’d like to see is to extend it beyond 20 years for the life of the project,” Autobee said. “We need to look at that.”

Board member Jim Gardner was assured by Gradisar that Pueblo County is guaranteed a voice in which projects are completed.

“They have a priority list and can’t switch unless both sides agree, as I understand it,” Gradisar said.

“This is a great opportunity to correct the issues,” said Mike Cafasso.

“What we said got listened to,” added Kevin McCarthy. “I think this is the best deal we’re going to get.”

From The Pueblo Chieftain (Chris Woodka):

Colorado Springs won’t need the full use of the Southern Delivery System for years, but some can’t wait for the $825 million water pipeline to be turned on.

Pueblo County commissioners heard testimony supporting a proposed agreement with Colorado Springs designed to settle issues surrounding the City Council’s decision to abolish its stormwater enterprise after the county had incorporated it into conditions for a 1041 permit in 2009.

“One in five people in Pueblo County live in Pueblo West and are impacted by SDS,” said Jerry Martin, chairman of the Pueblo West metro board. “With the newest break, we will depend on SDS for a very long time.”

Pueblo West joined the SDS project as a costsaving alternative to a direct intake on the Arkansas River downstream of Pueblo Dam. It shared in the cost of permitting and building the pipeline.
Last summer, it used SDS when its own pipeline broke.

Pueblo West’s main supply comes from the South Outlet Works and crosses under the river. The new break is more severe, Martin explained.

An agreement reached last summer allows Pueblo West to use SDS before it is fully operational, and settled some lingering legal issues related to Pueblo West’s partnership in SDS.

Security Water and Sanitation District, located south of Colorado Springs, also needs SDS to go online before summer, said Roy Heald, general manager of the district.

“Security has an immediate need for water because there are emerging contaminant in our wells,” Heald said.

Seven of the district’s 25 wells into the Fountain Creek aquifer were found to be contaminated earlier this year. The solution is to blend water from the Arkansas River with the well water to dilute contaminants. Right now, Security gets enough water from the Fountain Valley Conduit to make its supply safe. But in summer, water demands will increase, Heald explained.

Larry Small, the executive director of the Fountain Creek Watershed Flood Control and Greenway District, said the agreement paves the way for flood control projects seven years after the district was formed.

Small was on City Council when the stormwater enterprise was abolished on a 5-4 vote. He voted against eliminating the fee that was then in place. He was hired to run the Fountain Creek district two years later. The district has representatives from both Pueblo and El Paso counties.
The district was formed by the state Legislature out of concerns about the effect of El Paso County’s growth on Fountain Creek and the danger that is posed to Pueblo.

The $460 million for Colorado Springs stormwater projects over the next 20 years is needed to slow down Fountain Creek, but that doesn’t mean Pueblo would be protected. There are at least 18 projects south of Colorado Springs involving either detention ponds or dams that the district wants to get started on.

That process would get a kick start with $20 million in the next nine months if the agreement is approved by commissioners and Colorado Springs City Council in the next week. Three more payments of $10 million over the next three years would follow under terms of the 1041 agreement.

“This agreement says that we’re not just going to put something in place, but that we’re going to monitor it,” Small told commissioners. “It’s a cooperative, collaborative process. We don’t have to rely on rumors and innuendo.”

The city of Pueblo also would benefit from a potential $6 million in Fountain Creek dredging or levee maintenance projects that would cost the city only $1.2 million over the next three years. Pueblo Stormwater Director Jeff Bailey last week told The Pueblo Chieftain that the city has projects lined up, depending on how the funds are structured.

A separate $255,000 project to dredge between Colorado 47 and the Eighth Street bridge already is in the works. It would be funded by Pueblo County, the Lower Arkansas Valley Water Conservancy District, the Fountain Creek district and the state.

For Colorado Springs, SDS is a 40-year solution to provide water both for future growth and redundancy for the major water infrastructure it already has in place. Earlier comments to commissioners from Colorado Springs officials indicated only about 5 million gallons per day initially would flow through the SDS pipeline to El Paso County. It has a capacity of 75 million gallons per day.

Colorado Springs Mayor John Suthers said warranties on the project kick in when testing on SDS is completed at the end of this month, however, so Colorado Springs also would like to see the pipeline up and running by next week.