4 feet deep — and counting

Mile High Water Talk

Antero Reservoir already refilling with water; rehab project on track for late November 2017 completion.

By Katie Knoll

Crews work on final grading of Antero Dam in May 2016 following the installation of a new barrier wall inside the dam in 2015. Thanks to on-schedule construction timelines and a wet winter, the reservoir is expected to fill to a depth of 13 to 15 feet this year.

Last year, we emptied Antero Reservoir to clear the way for significant repairs to the 100-year-old dam. (Get the lowdown on the project by reading Draining Antero Reservoir: Where will all that water go?)

We’re happy to report that the project has persevered through harsh weather conditions and unpredictable construction timelines and remains on schedule. The current phase of the project — the installation of a barrier wall inside the dam — is on track to be completed by the end of…

View original post 122 more words

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s