Lake Nighthorse: “…there’s time, and there’s water time” — Charlie Smith

From The Durango Herald (Jessica Pace):

A 4.6-mile pipeline that will carry water from Lake Nighthorse to Lake Durango went to bid March 31, and construction is expected to start within a month.

“That side of the county really needs help, and that’s what La Plata West is going to do,” said Mardi Gebhardt, a La Plata West Water Authority board member. “Lake Durango is going to be our partner in treating the raw water.”

A 30-inch line will extend from Nighthorse’s north shore, cutting through Bureau of Reclamation land and private property along Wildcat Ridge to a booster pump station. There, an 8-inch line will make a right angle west, running parallel to Wildcat Canyon Road (County Road 141) before winding north to Lake Durango.

Tap fees and a Colorado Water Conservation Board grant will finance the $3.4 million project, which is a collaborative between Lake Durango Water Authority, La Plata West Water Authority and the Southern Ute and Ute Mountain Ute tribes.

Charlie Smith, general manager of Lake Durango Water Authority, said more than 100 customers are on the waiting list for taps.

“For our service area, this is enough to meet the demands and future demands in the system,” Smith said, referring to the many customers hauling water. The authority can pump 400 gallons per minute, depending on demand.

Early projections anticipated the project would be complete by the end of 2015, but as Smith said, “there’s time, and there’s water time.”

A pending final environmental assessment from the Bureau of Reclamation and negotiations with 16 property owners abutting the project is a large part of that…

The pipeline is the first mechanism that will pump water out of Lake Nighthorse and a first step to fulfilling a grander scheme to supply water, particularly to the tribes, which have the largest claims to Nighthorse water.

The agreement among the four stakeholders allows the Ute Mountain Utes to come back at a later time and extend the pipeline. Peter Ortega, legal counsel for the Ute Mountain Utes, said the pipeline is the first phase of moving water to where the tribe really needs it.

“We hope it eventually will reach the western edge of the reservation,” Ortega said. “It’s moving water slowly in our direction.”

Click here to read the draft EIS.

proposeddrysidepipelinefromlakenightnorse

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s