Arkansas Valley Conduit funding at risk

April 19, 2013

arkansasvalleyconduitproposed

From The Pueblo Chieftain (Chris Woodka):

The funding pipeline for the Arkansas Valley Conduit has sprung a leak. Federal funding pressures could reduce conduit funding to one-third of its current levels and far less than Southeastern Colorado Water Conservancy District officials had hoped for in next year’s budget. “The conduit is not the only project affected. There are projects under construction that got cut,” Southeastern lobbyist Christine Arbogast told the board Thursday. “Delays cost money, so it’s going to make it more difficult as we move forward.”

The district discussed a figure of $14 million to begin design and construction of the conduit in 2014. However, the budget President Barack Obama submitted to Congress last week included only $1 million for the conduit. The Bureau of Reclamation is on pace to complete an environmental impact statement for the conduit by the end of this year. But several other water projects already being built saw cuts of 75 percent or more in the president’s budget.

If Congress adopts another continuing resolution, rather than a budget, the conduit might retain its current level of funding, $3 million, in 2014, said Executive Director Jim Broderick. Otherwise, the district appears to be out of options to increase funding. “It’s clear the game is different than it used to be,” Broderick said, recounting last week’s visit to Washington, D.C. “This doesn’t stop the project, but it will move at a different pace.”

A federal law in 2009 provided a way to repay the federal government for conduit costs through storage contract payments to Reclamation for use of the Fryingpan-Arkansas Project. But payments would not start until after the project is completed.

The conduit could cost up to $500 million to build and would deliver fresh drinking water from Pueblo Dam to 50,000 people in 40 communities along the Arkansas River. “We’re concerned about the drop in funding, but we’re still in the pre-construction phase,” Broderick said.

More Arkansas Valley Conduit coverage here and here.


Salida: New wastewater treatment plant in production

April 15, 2013

salidacolorado

From The Mountain Mail (Casey Kelly):

Though improvements to the new Salida Wastewater Treatment Facility will not be fully completed for another couple of months, the city has begun treating wastewater at the new plant. The new facility began treating city water in November, and since then the city has been working to finish remaining improvements at the facility, Wastewater Plant Manager Randy Sack said Friday. Remaining improvements at the facility, which Sack said should be completed in the next “couple months,” include work on landscaping, the driveway, curb and gutter, phone and data lines, and painting.

Moltz Construction has been working on the new facility for the past 13 months, Sack said. “It’s working really nice,” he said. “It’s a little bigger. It’s doing a great job with the things we need it to do.”

Sack also said the new plant is all computerized, which allows easier monitoring of its operations. The previous plant was no longer meeting regulations for wastewater plants, City Administrator Dara MacDonald said. The plant was out of compliance with regard to levels of ammonia and biochemical oxygen demands, which Sack said “measure the organic strength of the wastewater.”

Sack said once the final improvements are made to the facility, the city plans to host an open house to invite the public to tour the new facility.

Sidebar on financials

The total cost of the Wastewater Treatment Facility upgrade project is $17.6 million. The project is being financed through a $12.1 million loan from the U.S. Department of Agriculture, a $1.35 million Department of Local Affair grant (with matching funds from the city) and a $2.6 million USDA loan the city received in 2009. The city will make its first payment on the $12.1 million loan in fall. The term of the loan is 40 years with an interest rate of 2.5 percent. At the time financing was originally approved, the interest rate was set at either 3.25 percent or the rate in effect at the time of the loan’s closing, whichever was lower. When the loan closed in February, the city secured the lower 2.5 percent interest rate. The city is required to make a minimum payment of $480,405 each year, but can make higher payments to lower the amount of total interest paid over the life of the loan. If the city makes only the minimum payments, it will pay $7.1 million in interest over the life of the loan.City Finance Director Jan Schmidt suggested at a February city council meeting that the city make payments that assumed the previous higher interest rate, which would have the city paying off the loan 8 months earlier and paying less money in interest.

City Administrator Dara MacDonald said when the city adjusted sewer rates, it was done in anticipation of the facility upgrade and the debt service that would come along with it. MacDonald said revenue from the city’s sewer enterprise fund is projected to cover the cost of the annual payments, along with the plant’s operation and annual maintenance costs.

Total 2012 revenues for the sewer fund came in at $1,444,641, and total expenditures, which included capital outlay costs for the facility’s construction this year, came in at $8,978,716. Excluding the one-time capital outlay costs this year, the sewer fund had $748,933 in expenditures, which would have resulted in net revenues of $695,708, enough to exceed the cost of the minimum annual loan payment.

More wastewater coverage here and here.


Water court: Subdistrict No. 1 pumpers can claim water from Reclamation’s Closed Basin Project

April 12, 2013

slvdischargerecharge.jpg

From The Pueblo Chieftain (Matt Hildner):

A water court judge ruled Wednesday that groundwater irrigators in the north-central San Luis Valley can claim water from a federal reclamation project to offset their pumping. The 45-page order from Judge Pattie Swift allows Subdistrict No. 1 to claim water from the Closed Basin Project, which pumps groundwater from the east side of the valley and sends it to the Rio Grande.

Objectors, which included five parties, argued, among other points, that the use of water from the project injured surface rights owners who were dependent on the Rio Grande and its tributaries.

Swift’s order said the project developed and delivered water to the Rio Grande that would have otherwise never made it to the river. “Thus the court cannot presume that pumping the Closed Basin Project wells causes injury to senior surface water rights,” the ruling said.

The subdistrict, which takes in more than 3,000 irrigation wells in the north-central valley, was created primarily to replace depletions to the river caused by pumping. The subdistrict purchased and leased over 10,000 acre-feet in 2012, including the Closed Basin Project water, and was ordered by the state engineer to return 4,724 acre-feet to the river.

In this year’s annual replacement plan, the subdistrict has again proposed using up to 2,500 acre-feet from the project toward its replacement obligations, although the proposal still requires approval of the state engineer.

More San Luis Valley groundwater coverage here and here.


[Drought] ‘It’s this slow, creeping death by 1,000 cuts’ — Chris Kraft #COdrought #ColoradoRiver

April 12, 2013

coloradobigthompsonmap.jpg

From the Northern Colorado Business Report (Steve Lynn):

A record crowd of 250 people attended the spring meeting of the Northern Colorado Water Conservancy District at the Ranch in Loveland. Farmers pleaded with Northern Water officials for at least 70 percent of their share of water from the Colorado-Big Thompson Project…

“The worst thing in the world for agriculture is a drought, which we’re in right now,” said Chris Kraft, a Fort Morgan dairy farmer. “It’s this slow, creeping death by 1,000 cuts.”

Northern Water board members are scheduled to decide Friday how much water they will distribute. Northern Water provides water to portions of eight counties with a population of 850,000 people and serves more than 640,000 acres of irrigated farm and ranch land. Farmers use about two thirds of the water coming from the project while cities use one third, while cities use one third, Northern Water spokesman Brian Werner said…

…Eric Wilkinson, Northern Water’s general manager, said that this year would mark the second time in the water wholesaler’s history that it would base its quota on “availability” of water rather than “need.”

Officials from several Northern Colorado cities argued at Thursday’s meeting that a quota of any more than 50 or 60 percent would overextend the already scarce resource. Donnie Dustin, the city of Fort Collins’ water resources manager, believes the city will face having a lower quota in future years if Northern Water adopts more than a 60 percent quota. However, Fort Collins doesn’t want Northern Water to go too low. The city would have to pass further water restrictions if Northern Water adopted a 50 percent quota, Dustin said…

Farmers contend that a 60 percent quota will mean planting fewer fields with crops that use more water, such as corn. That will have consequences for Weld County’s dairy industry, they say. “We got so many dairies in this country,” said Bill Markham, who farms corn, barley and sugar beets in Berthoud. “I don’t know where they’re going to get their feed.”

Kraft said a lower water quota would lead him to downsize his dairy farm. “If we don’t get the feed we need, we have to sell animals,” he said. “We’ll be shrinking down.”

From The Greeley Tribune (Eric Brown):

For only the second time in 56 years, the quota set for the Colorado-Big Thompson Project will be limited by how little water is available, rather than based on the demands of the region. After hearing suggestions from its water users Thursday, the Northern Colorado Water Conservancy District’s board of directors will set a quota for the C-BT Project today to determine how much water will be released this year from the system — which, with its 12 reservoirs, is the largest water supply project in the region. But, because reservoir levels are low and snowpack in the mountains is limited, the board will be restricted in how much water it can allow farmers and cities to use in 2013.

In nearly all years, the board can set a quota of 100 percent — although it rarely does — and still have at least some water in storage for the following years. But this year, a quota of 87 percent would deplete everything in the C-BT Project’s reservoirs, according to Brian Werner, a spokesman and historian with Northern Water. And the limited runoff from this year’s meager snowpack isn’t going help much, Werner added. The only other year the board has been so limited in the quota it could set was 2003 — following the historic drought year of 2002, said Werner, who’s been with Northern Water for more than 30 years.

Although C-BT water is limited this year, it’s still needed — particularly by farmers, many of whom cut back on production last year while battling drought, and fear they’ll have to plant even fewer acres this year because of the water shortages.

The historic predicament now facing the 12-member Northern Water board was brought on by the combination of continued drought, the board setting a historically high C-BT quota last year, the expectation of more dry weather, and because the region’s water demands are continually growing due to increased population, according to some of the experts who spoke at Thursday’s water users meeting. And, as water demands have increased, the availability of stored water hasn’t kept pace, added Werner.

Since the C-BT project went into use in 1957, the Northern Water board has set a quota every year in April to balance how much water could be used through the upcoming growing season and how much water needed to stay in storage for future years. The historic average for the C-BT quota has been just above 70 percent, according to Werner. A 70-percent quota means that for every acre-foot of water a C-BT shareholder owns, they’ll get 70 percent of an acre-foot to use throughout the year. An acre-foot is approximately 326,000 gallons of water.

Differences of opinion

Before setting its quota each year, the board takes suggestions from its water users. Thursday’s water users meeting drew about 250 people — a record-high attendance for Northern Water’s April meeting, Werner said. At the meeting, officials from local cities generally pushed for a quota of about 50-60 percent, wanting to keep it relatively low and save as much water as possible for the future. However, many farmers in attendance — who either are or will soon be planting crops, and need to know soon how much water they’ll have for the growing season — asked for a quota of about 70 percent.

The difference between a 50 percent water quota and a 70 percent quota amounts to more than 20 billion gallons of available water to northern Colorado.

Farmers said they’ll need as much water as possible to raise their crops and the feed needed by the region’s many dairies and feedlots. Many are worried that cutting back on planting again this year will have a negative trickle-down impact on the region’s overall economy — especially in Weld County, where agriculture is a $1.5 billion contributor. Each year, about two-thirds of the C-BT Project’s water goes to agriculture uses, but farmers and ranchers only own 34 percent of the water. To make up that gap, farmers and ranchers lease water from cities. However, because of the water shortages, many cities have said it’s unlikely they’ll have any extra water available in 2013.

Water officials from Greeley and Fort Collins said this would be the first time in about 10 years — dating back to 2003 — that they wouldn’t be able to lease extra water to local agricultural users. “You can get a flavor for the dilemma our board is in,” Eric Wilkenson, general manager of Northern Water, said to the crowd after hearing comments from concerned water users. But, with the C-BT’s overall reservoir levels 27 percent below average as of April 1, and snowpack in South Platte Basin 29 percent below average on Thursday and 24 percent below average in the Colorado River Basin, the Northern Water board can only do so much.

C-BT water flows to more than 640,000 acres of irrigated farm and ranch land and about 860,000 people in portions of eight counties, according to Northern Water numbers.

Last April, concerns for farmers led the board to declare a 90 percent quota for C-BT water, the highest set in April since 1977. As drought persisted, the Northern Water board increased the C-BT water quota to 100 percent in May. The board could set that quota then because reservoir levels were high, due to above-average snowpack in previous years. With last year’s heavy water usage, reservoir levels dropped and are now expected to stay low since little snow has accumulated in the mountains.

More Northern Colorado Water Conservancy coverage here and here.


Aspinall Unit operations update: Diversions through the Gunnison Tunnel bumped to 600 cfs #ColoradoRiver

April 11, 2013

fogfilledblackcanyonofthegunnisonnps.jpg

From email from Reclamation (Erik Knight):

A recent flow measurement by the USGS has shown us that the Gunnison River below the Gunnison Tunnel is currently running around 375 cfs. The Uncompahgre Valley Water Users could use more water to keep up with irrigation demands. Therefore, tomorrow morning, April 11th, diversions to the Gunnison Tunnel will increase by 75 cfs or so, leaving 300 cfs in the Gunnison River below the Gunnison Tunnel. There will be no change to Crystal releases. After this increase in diversion, flow in the Gunnison Tunnel should be around 600 cfs.

More Aspinall Unit coverage here and here.


Colorado Springs Utilities plans to spend $6 million on efforts to mitigate the Waldo Canyon burn scar

April 10, 2013

waldocanyonfirejuly2012

From the USDA Blog (Mike Stearly):

The U.S. Forest Service and Colorado Springs (Colo.) Utilities recently announced a new 5-year partnership to help restore the areas burned by the devastating Waldo Canyon Fire that tore through part of the west side of the city in 2012.

Through the partnership, Colorado Springs Utilities will invest approximately $6 million in support of the watershed health goals and activities over the next five to 10 years. The Forest Service will complete on-the-ground project planning and treatment in areas that complement Colorado Springs Utilities investments.

During an event at the Flying W Ranch – a 60-year-old tourist attraction destroyed in the fire – Harris Sherman, USDA Under Secretary for Natural Resources and Environment, met with Congressman Doug Lamborn, U.S. Senators Mark Udall and Michael Bennett, and representatives from the Coalition for the Upper South Platte, El Paso County Commissioners and the city of Colorado Springs.

“This partnership will ensure improved water quality for the residents of Colorado Springs,” Sherman said. “Collaborating on watershed restoration will have a long-term positive impact on forest and watershed health and allows us to accomplish more on-the-ground projects.”

The innovative partnership between Colorado Springs Utilities and the Forest Service is preserving and protecting crucial watersheds that provide water to Colorado’s second largest city. The signing of the agreement establishes work to reduce wildfire risk, restore burned areas, minimize erosion impacts and coordinates pre-suppression wildland fire efforts.

“This agreement … solidifies a critical partnership with the Forest Service, a partnership that has benefited our water supply and community for decades,” said Gary Bostrom, chief water services officer for Colorado Springs Utilities. “Our ongoing relationship with the Forest Service will help us channel customer rate dollars in the most efficient way possible to protect our most vital resource and the forest that surrounds it.”

The human-caused Waldo Canyon fire started June 23, 2012, and left a scar of more than 18,000 acres, cost millions of dollars to fight, caused the evacuation of 32,000 people, destroyed 346 homes and killed two people. The fire has since been labeled the largest, most expensive and destructive fire in Colorado’s history.

More Colorado Springs Utilities coverage here and here.


Remediation work has been unsuccessful at Silver Bell Mine tailings site

April 9, 2013

redmountainpass.jpg

From The Watch (Gus Jarvis):

A settlement was reached late last month between Sheep Mountain Alliance and PacifiCorp that obligates the company to investigate and take further remediation actions on the Silver Bell Tailings located near the Ophir turn on U.S. Hwy. 145.

Since 1998, PacifiCorp has taken voluntary steps to cap, stabilize and clean the mine tailings deposited by the Silver Bell Mill in the 1950s. For the past two years, that completed remediation work on the tailings have been in a monitoring stage. So far, the remediation work has been unsuccessful in keeping the Environmental Protection Agency’s water quality standards for the San Miguel River at acceptable levels.

Roughly one year ago, when, according to Sheep Mountain Alliance Director Hilary Cooper, the organization was “combing” through EPA water data from the San Miguel River, downstream from the tailings, “alarming” records they believed to be Clean Water Act violations turned up.

SMA eventually brought a citizen Clean Water Act lawsuit against PacificCorp , alleging liability due to years of illegal discharges of heavy metals, acidic drainage and other pollutants from the impoundment. All of those mine contaminants, the lawsuit alleged, were flowing out of the Silver Bell Tailings impoundment and into the Howard Fork of the San Miguel River, despite the remediation work that had been completed on the site.

The lawsuit eventually led to a mediation process between SMA and PacifiCorp, resulting in a settlement and a consent decree announced March 21. In the settlement, both parties agreed to use a third-party expert to analyze and recommend a way forward that both parties could agree on. PacifiCorp has agreed to embark on four-step monitoring process of the tailings that will determine where the specific source of the contamination is located; once that is found, PacifiCorp will come to the table with a proposed correction.

“What we believe is that it will lead to a replacement of the tailings cap,” Cooper said. “But this way, with an in-depth analysis of the contamination sources, we think a new cap will be engineered in a way that will have a higher chance at success than what is there right now.”[...]

In addition to the management plan action, PacifiCorp has also agreed to pay $150,000 to the San Miguel Watershed Coalition. Under federal law, polluters found accountable under the Clean Water Act are required to pay funds in lieu of civil penalties toward local watersheds. The funds will be applied to the restoration of the Priest Lake reservoir.

More water pollution coverage here.


Colorado Parks and Wildlife prepares to reclaim Miramonte Reservoir in SW Colorado; bag, possession limits removed

April 9, 2013

miramontereservoircpw.jpg

Here’s the release from Colorado Parks and Wildlife:

Illegal stocking of smallmouth bass in Miramonte Reservoir will force Colorado Parks and Wildlife to partially drain the lake and treat it with an organic pesticide to kill all the fish early this fall. Restocking will occur shortly after the treatment is completed.

The good news for anglers is that as of April 1 all bag and possession limits will be removed for smallmouth bass and trout until the treatment begins.

“This emergency public salvage will allow licensed anglers a unique opportunity to catch and keep these fish prior to the treatment,” said Eric Gardunio, aquatic biologist in Montrose.

Miramonte Reservoir is located in San Miguel County about 10 miles south of Norwood in western Colorado. The reservoir is one of the most productive stillwater trout fisheries in the state and people travel from throughout the West to catch the rainbow and brown trout that regularly grow to quality size. The lake is also a popular destination for crayfish enthusiasts. Miramonte accounts for about 20,000 angler days every year which contributes $1.5 million to the economy of San Miguel County.

The illegal stocking of smallmouth bass has threatened the trout fishery and crayfish, as well as native fish downstream in the San Miguel and Dolores rivers, prompting action by Parks and Wildlife.

During the salvage anglers must have a 2013 Colorado fishing license and only hook and line methods of take will be permitted. The use of explosives, toxicants, firearms, seines, nets, snagging or electricity is prohibited. Signs will be placed at access points around the lake to notify anglers of this temporary regulation change.

“The trout fishing following ice-off around April 1 should be productive and anglers should take home good numbers of the pink-fleshed Miramonte trout,” Gardunio said.

As the reservoir is drained beginning in May, angler access may become difficult due to exposed mud flats. Boat access will be limited as ramps will eventually become unusable as the water level drops. Interested anglers are encouraged to utilize the fishery early in the year to avoid access issues later in the season.

This emergency salvage is a part of an effort by Parks and Wildlife to maximize angling opportunities in the short term while rebuilding the trout fishery at Miramonte as soon as possible.

“Treating the reservoir is something we wish we didn’t have to do, but we know we must,” said Renzo DelPiccolo, area wildlife manager in Montrose. “People who illegally move fish into lakes, ponds and rivers are not only committing a criminal act, they are endangering native species, stealing a resource and recreational opportunity from thousands of anglers and negatively impacting the local community.”

The chemical treatment, using Rotenone, is scheduled for early fall and the reservoir will be opened for fishing until that time. The date of the treatment will be announced late in the summer. During the treatment the reservoir will be closed for public safety. The reservoir will be drawn down and Rotenone will be applied to the remaining water and feeder streams to kill all of the fish. Rotenone breaks down quickly in the environment and poses no threat to vegetation or non-aquatic species.

Biologists will restock the lake with fish as soon as the pesticide has dissipated; a quick recovery of the trout and crayfish fisheries is expected.

“Miramonte is a very productive fishery where trout can grow ten inches or more in a single year,” Gardunio said. “We expect the catchable and sub-catchable trout we stock following the treatment to be up to quality size within a year of re-stocking.”

“This reservoir is managed as a put-and-grow trout fishery and that management strategy will not change,” explained John Alves, senior aquatic biologist for the southwest region for Colorado Parks and Wildlife. “Under this management strategy we can provide an excellent angling opportunity at a low cost to anglers.”

Smallmouth bass, which are a warmwater predator fish, were illegally stocked in the reservoir sometime before 2011 and reproduction has been documented. A recent survey showed that in one year smallmouth bass have increased in abundance from 5 percent to 44 percent of the fishery.

“The bass are now a top predator in the lake. They compete with trout for food and space, and consume trout and crayfish,” Alves said. “If left alone, the bass could eventually devastate Miramonte as a trout fishery. Furthermore, the habitat, prey base and water temperature will not support a quality bass fishery in the long term. So, once an illegally stocked fish population has become established, the only recourse is to start over by using a fish pesticide to kill all the fish in a lake.”

In addition to impacting a renowned sport fishery, the smallmouth bass also pose a threat to downstream native fish. An agreement between the state of Colorado, U.S. Fish and Wildlife Service and neighboring states restricts stocking of non-native warm water fish without a permit because of the danger they pose to native and endangered fish.

Miramonte Reservoir is located above the San Miguel and Dolores rivers which support important populations of three native fish species that biologists are working to protect: the roundtail chub, the bluehead sucker and the flannelmouth sucker. These native fish are found only in desert rivers of the western United States. Changes in the river system such as dams, pollution, water withdrawals, competition and predation from non-native species have caused these fish to decline in range and numbers.

“Native species are needed to help maintain the natural health and balance of any ecosystem. If a species is lost it affects the health of other plants and animals, and changes a natural ecosystem forever,” Alves said.

CPW aims to maintain healthy native fish populations not only for the benefit of native ecosystems and the people of Colorado, but also to prevent unwanted federal management of these species under the Endangered Species Act.

“Illegal stocking carries serious consequences that can have long-lasting negative effects on both fisheries and local communities,” DelPiccolo said.

Anyone who has information about illegal fish stocking at Miramonte Reservoir or at any other water in Colorado should contact the Parks and Wildlife office in Montrose at 970-252-6000, or call Operation Game Thief at 1-877-265-6648. Tips can be made anonymously and cash rewards are possible.

To read a full fisheries management report about Miramonte Reservoir, see: http://wildlife.state.co.us/SiteCollectionDocuments/DOW/Fishing/FisheryWaterSummaries/Summaries/Southwest/MiramonteReservoir.pdf.

For more information about fisheries management in Colorado and aquatic nuisance species, see: http://wildlife.state.co.us/FISHING/Pages/Fishing.aspx.


Will Lake Nighthorse recreation facilities be online in by 2014?

April 9, 2013

lakenighthorseusbr.jpg

From The Durango Herald (Jim Haug) via the Cortez Journal:

Almost two years after the reservoir was filled in June 2011, local government officials have not allowed kayaking, bird watching or mountain biking on the 5,500-acre site. Lake Nighthorse might be a case of politics proving to be a bigger obstacle than the laws of physics.

About two miles from downtown Durango, the lake is a temptation for all kinds of outdoor enthusiasts, but it is not yet accessible to the public. Officials now are saying 2014, but they have delayed the opening before.

To venture onto the property without permission literally is a federal offense, although judging by footprints and pawprints, people and their dogs apparently have made the trek. “We’ve had to chase out people with kayaks and canoes,” said Tyler Artichoker, facilities manager for the U.S. Bureau of Reclamation…

After budgeting almost $200,000 to open the lake this summer, Durango Parks and Recreation Director Cathy Metz laid out a series of complications that has moved the goal of opening the lake to the summer of 2014. The city first must annex the land so it can provide law enforcement. The Bureau of Reclamation must approve a lease agreement with the city and do an environmental assessment of the city’s master recreation plan, which was developed after much public input and consensus building about the kinds of recreation to allow. Jet skis are out. The master plan calls for a “family beach” to distinguish it from other kinds of beaches. The bureau’s environmental assessment then must be made available for public comment, which is expected to happen in April.

Once the bureau signs off on the lease agreement, the city plans to get assistance from the Colorado National Guard for help with land clearing. An entrance station and boat-inspection area also must be built with funding from a state grant…

“If you can name a governmental entity, it has a stake in Lake Nighthorse,” Rinderle said.

More Animas-La Plata Project coverage here and here.


HB13-1044 (Authorize Graywater Use) passes the state house, now on to the state senate

April 9, 2013

graywatersystem.jpg

From email from State Representative Randy Fisher:

I’m pleased to announce that one of my top priority bills for the 2013 legislative session, HB-1044, was passed in the House on third reading on April 5. If the bill becomes law, it will authorize the use of graywater recycling in Colorado and will provide Coloradans with a powerful and readily available water conservation tool.

HB-1044 has its roots at CSU where professors Larry Roesner and Sybil Sharvelle have conducted foundational research and development on graywater systems. Drs. Roesner and Sharvelle are the co-directors of the Urban Water Center at CSU’s Department of Civil and Environmental Engineering. Both professors have spent countless hours at the Capitol advocating for passage of HB-1044. They have earned my respect and gratitude for their efforts to help write and advocate for the bill.

“Graywater” consists of the discharge from fixtures other than toilets, kitchen sinks, and dishwashers that is collected and recycled within residential, commercial, or industrial facilities with minimal treatment in accordance with public health standards. HB-1044 amends Colorado’s public health statutes to allow more efficient first-use of water by enabling the recycling of graywater within the facilities in which it is generated. Graywater reuse is an important municipal and industrial water conservation tool that has the capability of reducing per capita water consumption by up to 30%.

The Coloradoan newspaper had a very positive editorial about HB-1044 in its Sunday, February 3, edition. Here is a link to the article:

http://www.coloradoan.com/article/20130202/OPINION01/302020020/Editorial-Fischer-leading-way-water-bills.

A critical vote on the HB-1044 occurred last week when the House Appropriations Committee voted to approve a small general fund appropriation required by the health department for rulemaking. The approval of the appropriation paved the way for consideration of the bill in the House. The Senate will begin deliberation on HB-1044 in the coming days.

More 2013 Colorado legislation coverage here.


Grand Junction: Aspinall Unit operations meeting April 25

April 8, 2013

gunnisontunnelnps.jpg

From email from Reclamation (Dan Crabtree):

The Uncompahgre Valley Water Users began diversions through the Gunnison Tunnel [last] week. Consequently, releases from Crystal Dam are about 750 cfs, the Tunnel is currently diverting about 400 cfs, with the balance through the Canyon/Gorge. Reclamation plans to continue to operate in accordance with the Aspinall Operations Record of Decision and to allow the Black Canyon Water Right to be met. As the Tunnel increases diversions over the next few weeks, mild fluctuations in the Gunnison River in the Canyon/Gorge may occur.

The April 1 Blue Mesa forecast for unregulated April through July runoff is 315,000 ac-ft which is 47% of average. The April Operations Meeting will be held on April 25th in Reclamation’s Western Colorado Area Office, 2764 Compass Drive Suite 106, beginning at 1:00 p.m.

More Aspinall Unit coverage here and here.


Permitting water projects: ‘…maybe we’re having the federal government check too many boxes’ — Randy Ray

April 8, 2013

nisp2

From The Greeley Tribune (Eric Brown):

New water-supply projects could come to fruition much faster if a Colorado congressman has his way in Washington. Rep. Cory Gardner, R-Colo., is piecing together a bill aimed at speeding up the federal permitting process for new water endeavors, if they are endorsed by the governor of that state.

Many regional water projects have been in the federal permitting stages for years, with participants having spent millions of dollars along the way, and they still have no guarantee the projects will be built.

Brian Werner — a spokesman for the Northern Colorado Water Conservancy District, which is overseeing efforts to build the Northern Integrated Supply Project, or NISP — said the project has been in its federal permitting phase since 2004, with the 15 participating cities and water districts having already spent about $12 million. He suspects the process will go on for yet another year. Gardner said it’s taking “way too long.”

The details of his bill aren’t finalized, but Gardner said it could call for federal agencies to say “yay” or “nay” on a proposed water project within six to nine months after a governor puts his support behind it.

Colorado Gov. John Hickenlooper has yet to endorse NISP, which would supply its partners with 40,000 acre feet of new water supplies annually, if ever built.

Opponents say water-storage projects like NISP could interfere with river flows and impact wildlife, fisheries, forests and recreational use.

Gardner and others say that — with future water shortages expected for a number of regions — new water-supply projects must get a “yay” or “nay” quicker, so those projects can get built or participants can go back to the drawing board. Agriculture, the biggest user of water, will suffer the most if these lulls continue, Gardner added.

Participants of large-scale, water-supply projects must work with the U.S. Army Corps of Engineers, Environmental Protection Agency, U.S. Fish and Wildlife and others to make sure all needed wildlife-, habitat- and environmental-protection measures are taken before dirt is moved. “No doubt; mitigation efforts need to be taken,” said Randy Ray, executive director with the Central Colorado Water Conservancy District in Greeley. “But maybe we’re having the federal government check too many boxes.

“I’d like to see the federal government have more faith in the state, the local water districts and the engineers who are working on these projects.”

Without new water-supply projects in the region, farmers and some water experts worry that growing cities will continue buying up farmland and agricultural water rights in the future to meet their growing needs.

The Colorado-Big Thompson Project, the largest water project in northern Colorado, has seen its water go from 85 percent owned by agricultural users, to now 34 percent owned by agricultural users. Many farmers have sold rights in times when farming wasn’t profitable. Farmers who need water today now depend on leasing it from the cities who own it. But in dry times, like this year, cities say they don’t have enough water in storage to lease to agriculture.

If Colorado had NISP-like projects in place already, Werner and others say, the above-average snowpacks of recent years would have filled those reservoirs, local cities and farmers would have more water in storage now and they would be in much better shape to endure the ongoing drought. Instead, during 2009, 2010 and 2011, a total of about 1.4 million acre-feet of water above what’s legally required flowed from Colorado into Nebraska, according to Werner. “Even if we could have captured just some of that in new reservoirs, how much better off would we be right now?” Werner asked.

Colorado’s ag industry has a $40 billion impact on the state, the second-largest contributor to Colorado’s economy, behind oil and gas.

But according to the 2010 Statewide Water Initiative Study, the South Platte River basin in northeast Colorado could lose as much as 190,000 acres of irrigated farmland by 2050 due to water shortages. Farmers and water experts agree that conservation and water-sharing projects could help Colorado meet its growing water needs, but they say new water-storage projects will also be needed.

Ray didn’t want to comment specifically on Gardner’s bill, but he stressed the need to speed up the federal permitting process for new water projects. He explained that the Central Water and others have been discussing the Chatfield Reservoir Reallocation Project since the 1980s, but are still working with the federal government to get all permitting in order. “It needs to change,” he said “Because we’re not getting anywhere.

“And we really need to get somewhere.”

More Northern Integrated Supply Project coverage here and here.


San Luis Valley: Groundwater Sub-District #1 plans to fallow 9,073 acres to reduce pumping by 15,600 AF

April 5, 2013

slvdischargerecharge.jpg

From The Pueblo Chieftain (Matt Hildner):

A groundwater subdistrict designed to reduce aquifer pumping and protect surface water users released its draft annual replacement plan Thursday. The plan for Subdistrict No. 1, which takes in just under 3,400 irrigation wells in the north-central San Luis Valley, is subject to public comment and must still be approved by the state engineer. The subdistrict has set a 7 p.m. meeting Thursday, April 11, in the Adams State University Student Union to take public comment.

The draft plan projects the subdistrict will send 5,102 acre-feet of water into the Rio Grande to mitigate the impacts to surface water users from groundwater pumping. Groundwater pumping by subdistrict wells is estimated to come in at 270,000 acre-feet this year. The plan lists 10 sources for the replacement water that amount to 11,165 acre-feet in available water. One of those sources is a U.S. Bureau of Reclamation project that pumps groundwater from the eastern side of the valley and delivers most of it to the Rio Grande to assist with interstate compact requirements. The subdistrict’s ability to use water from the Closed Basin Project remains under review by the Division 3 Water Court.

The subdistrict’s other main goal is to reduce groundwater use through the fallowing of agricultural land. It has contracts with landowners to allow the fallowing of 9,073 acres this year, a move that is projected to reduce pumping by 15,600 acre-feet.

More San Luis Valley Groundwater coverage here and here.


Colorado River Basin: Denver Water, et. al., are operating under the Shoshone Outage Protocol

April 4, 2013

shoshoneglenwoodcanyon.jpg

Here’s the release from Denver Water (Stacy Chesney/Travis Thompson):

Two back-to-back, drought-plagued winters in Western Colorado have triggered an agreement to “relax” a senior water rights call on the Colorado River at the Shoshone Hydro Plant to allow water providers to store more water this spring, a move that benefits Denver Water and the West Slope.

The Shoshone Hydro Plant is owned by Xcel Energy and is located in Glenwood Canyon. Its senior 1902 water right of 1,250 cubic feet a second (cfs), when called, is administered by the Colorado Division of Water Resources against junior water storage rights upstream that include Denver Water’s Dillon and Williams Fork Reservoirs, the Colorado River District’s Wolford Mountain Reservoir and the Bureau of Reclamation’s Green Mountain Reservoir.

The agreement “relaxes” the call to 704 cfs when river flows are low, or takes a Shoshone call totally off the river when flows are rising, which is the current situation. This practice gives the upstream juniors water rights holders the ability to store water once the spring runoff begins in earnest. Currently, the Colorado River is flowing through Glenwood Canyon at about 825 cfs. (The long-term historical average for this date is about 1,150 cfs.)

Two tripping points activate the agreement: when Denver Water forecasts its July 1 reservoir storage to be 80 percent of full or less, and when the Colorado River Basin Forecast Center predicts spring runoff flows at Kremmling in Grand County will be less than or equal to 85 percent of average. Currently, the reservoir forecast is 74 percent full on July 1 and the Kremmling forecast is 60 percent of average.

Denver Water has already enacted its Stage 2 Drought Restrictions to limit outdoor water use and enact other conservation measures.

The winter of 2012 was the fourth worst on record in the Colorado River Basin and 2013 has been tracking just as poorly. The only improvement between the two winters occurred in March 2013 as storms continued to build snowpack. By this time in 2012, runoff was already under way.
The relaxation period is between March 14 and May 20, in deference to boating season on the river and irrigation needs in the basin.

As for the water that Denver Water gains by the relaxation, 15 percent of the net gain is saved for Xcel Energy power plant uses in the Denver Metro Area and 10 percent is delivered to West Slope entities yet to be determined by agreement between Denver Water and the Colorado River District.

“This is a statewide drought, and we all need to work together to manage water resources for the health and safety of our residents, our economic vitality and the environment,” said Jim Lochhead, CEO/manager of Denver Water. “The Colorado River Cooperative Agreement and the Shoshone Outage Protocol are great examples of the partnership between Denver Water and the West Slope to do just that. Last year, even though the CRCA was not yet in effect, Denver Water released water to the river even though the Shoshone Power Plant was not operating and the call was not on. This year, under the Denver Water-Xcel Energy agreement, the Shoshone call will be relaxed.”

“Relaxing the Shoshone water right in this limited way benefits the West Slope as well,” said Colorado River District General Manager Eric Kuhn. “It might make the difference between having a full supply at Green Mountain Reservoir and not having a full supply. In a year like this every extra drop of water we can store now will help us later.”


‘The unpredictable nature of snowpack and rainfall…underscores the need for more water storage’ — Cory Gardner

April 4, 2013

nisppreferredalternative.jpg

From the Denver iJournal (J.D. Thomas):

With Colorado cities facing austere watering restrictions and farmers unable to plant crops this year, U.S. Rep. Cory Gardner, R-Yuma, believes the wait for a decision on the Northern Integrated Supply Project has gone on too long.

“The unpredictable nature of snowpack and rainfall in Colorado underscores the need for more water storage in good years, so we are better prepared for the bad ones,” said Garner who is hoping to hurry along a U.S. Army Corps of Engineers decision regarding the project. “NISP would provide the water storage we need to support northern Colorado’s growing communities and provide protection to farmers and families when the weather turns dry.”

An Environmental Impact Study process conducted by the U.S. Army Corps of Engineers for the project has already taken nine years and cost the participants about $11 million. The congressman is currently drafting water-storage legislation to streamline the approval process for projects like NISP, according to a statement from his office.

“This will ensure that these projects don’t drag on for decades and waste millions of dollars,” said Rachael Boxer-George, Gardner’s spokeswoman. “We are going to set a deadline on when the initial application needs to be approved or denied. The length of the EIS process is being discussed as we draft this bill, but so far we’re focusing on just the permits.”

Ten-year waits on an EIS are certainly not unprecedented, for instance the Northern Colorado Water Conservancy District has gone through a similar wait on the Windy Gap firming project. But as growing municipalities on the Front Range seek new quality water sources, the undammed Cache-La Poudre is a natural place to look, and participants in NISP includes not only Weld and Larimer county water districts and municipalities, but also Erie, Lafayette and the Left Hand water district in Boulder County.

Though the two project elements will not actually dam the Poudre, the project has also attracted substantial opposition, including Western Resource Advocates of Boulder. That organization has suggested a program of water conservation, reuse of municipal water and transfer and coordinated use of agricultural water could provide the same amount of water while maintaining the riparian ecosystem of the Poudre.

“I certainly hope the congressman doesn’t believe that he can cut out public input on this process,” said Laura Belanger, the water resources engineer with the Boulder environmental organization.

More Northern Integrated Supply Project coverage here. More Windy Gap Firming Project coverage here.


Greenland Ranch non-tributary Denver Basin groundwater is a potential source developers

April 3, 2013

denveraquifer.jpg

From the Colorado Springs Business Journal (John Hazlehurst):

When Philip Anschutz acquired The Broadmoor in 2011, he also acquired other significant assets owned by Oklahoma Publishing Co., including adjudicated water rights to non-tributary water beneath 7,640 acres of the Greenland Ranch in Douglas County, just north of Monument Hill off Interstate 25.

The ranch, one of the largest tracts of undeveloped land between Denver and Colorado Springs, has had a tangled history. First settled 150 years ago, it remained the property of the Higby family until 1980, when it was sold to a partnership that included Treasury Secretary William “Bill” Simon, Oklahoma businessman Ed Gaylord and Colorado Springs developer Bruce Shepard.

The partnership’s development plans fizzled, as did plans to develop the property’s subsurface water resources. In 2000, the entire 21,000-acre ranch was purchased by the Conservation Fund in a complex partnership with Great Outdoors Colorado, Douglas County, Colorado Division of Wildlife, Colorado State Parks, and Denver billionaire John Malone. The property is protected by a conservation easement, which forbids surface development in perpetuity.

But on the portion of Greenland Ranch formerly owned by Gaylord, water rights were severed from surface rights. A confidential memo offering the rights for sale prior to Anschutz’ acquisition describes the process:

“As part of the sale of the Greenland Ranch in 2000, Sun Resources Inc., a subsidiary of The Oklahoma Publishing Company, reserved the right to all non-tributary groundwater beneath 7,640 acres of the Ranch. The water right entitles the owner to withdraw 1 percent of the total amount per year (14,562 acre-feet) for 100 years. The right is decreed as non-tributary and, therefore is not subject to surface water priorities. In addition, (Sun) has completed significant legal work, as well as preliminary engineering, technical and market analysis. These work products and reports will be transferred with the water right. The right has accompanying surface land easements for well field, treatment facilities, and pipeline infrastructure development that will also be conveyed in the sale. As a result, no further legal proceedings are necessary to develop and sell the water.”

The 14,562 acre-feet would be roughly equivalent to 20 percent of Colorado Springs’ current annual needs…

Last fall, Sun Resources, now an Anschutz-owned company charged with developing the water rights, drilled two deep test wells on the Greenland Ranch property to confirm 1995 estimates of available water. One well, tapping the Arapahoe aquifer, was drilled to a depth of 2,040 feet, and flowed at a rate of 650 gallons per minute during a 72-hour test. The other targeted the Denver aquifer at 1,490 feet and flowed at 350 GPM. These results tended to confirm the 1995 estimates, said Sun CEO Gary Pierson. “We’ve completed those test wells,” said Pierson, “and now we’re in some very intense discussions with interested parties.”[...]

Full development of the water rights would be expensive. Dozens of production wells would have to be drilled throughout the property, power delivered to wellheads, and pump stations and pipelines built to transport the water to potential users…

Should communities rely upon non-renewable resources such as Greenland Ranch groundwater? Colorado Springs Utilities executive Gary Bostrom doesn’t think so.

“That depends on how it might integrate into an existing supply mix,” said Bostrom, who heads the CSU water resources department. “We have well fields, but the value (of non-renewables) is as a supplemental source. That may be attractive to some districts.”[...]

Despite being a non-renewable source, Greenland Ranch water may be attractive to potential users. Making a deal with Anschutz is not like making a deal with an ordinary promoter — you know Anschutz can deliver. His ability to fund a $100 million project is not dependent upon commitments from skittish lenders, or upon the solvency of unrelated parties to any deal.

The water is also of high quality, according to a 2009 independent analysis. It’s low in dissolved solids and uncontaminated by industrial pollutants. That quality likely will remain unchanged, since there will be no surface development either on or adjacent to the property…

Greenland Ranch water, decreed as non-tributary, therefore is not subject to surface water priorities, or any restrictions on its use. In its sweeping 1995 decree, the Water Court couldn’t have been more explicit. “19. Appropriation Doctrine Inapplicable. The rights to groundwater determined herein are not subject to and shall not be administered in accordance with the prior appropriation doctrine or any priority of appropriation. C.R.S. 37-92-305 (11).” The Water Court retains jurisdiction over any eventual Greenland water plan and, based on analysis of drilling results, may adjust the annual withdrawal rate. Pierson appears to believe any adjustment will be upward, mentioning a figure of 17,500 acre-feet annually. CSU’s Bostrom cites 10,000 acre-feet as more likely.

More Denver Basin Aquifer System coverage here and here.


Colorado-Big Thompson Project operations update: 80 cfs in the Big Thompson below Olympus Dam #coriver

April 2, 2013

coloradobigthompsonmap.jpg

From email from Reclamation (Kara Lamb):

Over the weekend, releases from Olympus Dam to the Big Thompson River bumped up slightly. We are now sending about 80 cfs down through the canyon. We are collecting about 50 cfs at the Dille Diversion Dam and sending it on to Horsetooth Reservoir.

We are running some Colorado-Big Thompson Project water through the canyon while some routine maintenance is being conducted on the Charles Hansen Feeder Canal. When the work wraps up in a couple of weeks, we will begin moving water back through the canal rather than running it down the canyon.

To learn more about Lake Estes and Olympus Dam, please visit our website. Data on this website is updated every night at midnight.

More Colorado-Big Thompson Project coverage here and here.


Rio Grande Compact Commission meeting recap: ‘My mantra has been let’s try to solve and not fight’ — Scott Verhines

March 31, 2013

riograndebasin100thmeridianorg

From the Valley Courier (Ruth Heide):

Alamosa hosted the annual Rio Grande Compact Commission meeting, which rotates among the states of Colorado, New Mexico and Texas.

Although the states are currently involved in litigation over compact administration, pending lawsuits were hardly mentioned during the meeting, and state engineers said they hoped the states could resolve their differences.

In January, Texas filed suit against New Mexico over Rio Grande Compact disputes, with Colorado caught in the middle since it is part of the compact. The suit alleged New Mexico was not delivering to Texas the water owed that state under the compact.

“I am just hoping the three states and the commission continue to endeavor to work in a cooperative way,” said Dick Wolfe, compact commissioner for Colorado and the state water engineer.

Scott Verhines, Wolfe’s counterpart in New Mexico, said, “My mantra has been let’s try to solve and not fight … It behooves all of us to look for an opportunity to solve rather than fight.”

Pat Gordon, Texas’ compact commissioner and state engineer, said although he could not elaborate on all of the litigation issues, he agreed with Wolfe’s desire “that hopefully we can resolve all these issues.”

He said, “Water would solve a lot of issues.”

That seemed to be the consensus of all three states, which are entering yet another substandard water year.

“This is our fifth year in a row, consecutive year in a row, of below average conditions,” Commissioner Wolfe said. “We are seeing some pretty sustained below average conditions which certainly makes it difficult not only for users in Colorado but our downstream states as well.”

He said in the last 10-12 years, there have only been two or three years above the long-term average.

Wolfe reminded the water commissioners that 2012 experienced below average flows on the Rio Grande and Conejos River systems, with the Rio Grande producing 65 percent of average and the Conejos system 56 percent. He said 2013 will continue in a similar fashion but may be slightly better than last year. The March 1 forecast predicted 70 percent of average flows on the Rio Grande and 69 percent on the Conejos system, he reported.

More Rio Grande River Basin coverage here and here.


USFWS designation of habitat for the flycatcher was the talk of the recent Rio Grande Compact meeting

March 31, 2013

southwesternwillowflycatcherdesignatedhabitatusfws

From the Valley Courier (Ruth Heide):

The U.S. Fish and Wildlife Service (FWS) recently designated critical habitat for the Southwestern Willow Flycatcher in portions of the San Luis Valley totaling 27 miles and nine miles along the uppermost portion of New Mexico’s Elephant Butte Reservoir, one of the main storage facilities for the Rio Grande Compact. Murphy said the Colorado and New Mexico designations were essential to the recovery of the species, which has been on the federal endangered species list since 1995. Commissioners expressed concern the designations would affect compact administration. Murphy indicated the designations should not affect water administration along the Rio Grande [ed. emphasis mine].

In the engineer advisers’ report to the compact commission on Thursday, Colorado’s Engineer Adviser and Colorado Division 3 Engineer Craig Cotten read into the record the advisers’ report, which included the concern the Elephant Butte Reservoir flycatcher designation could impact about one million acre feet of reservoir storage. “Information presented by the [Fish and Wildlife] Service and [Bureau of] Reclamation relating to the impacts of the designation upon reservoir operations was inconclusive,” Cotten read from the engineer advisers’ report. “The engineer advisers are concerned about impacts from the designation on certain elements of the Rio Grande Compact, and to water operations, including supplies at Elephant Butte Reservoir.”

Colorado Commissioner and State Engineer for the Colorado Division of Water Resources Dick Wolfe questioned Murphy why areas in the San Luis Valley had been designated critical habitat for the flycatcher since members of the water community had worked for many years developing a habitat conservation plan (HCP) precluding the need for that designation. Wolfe said the Fish and Wildlife Service had been involved in the habitat conservation plan process and had approved it. “In approving that HCP the service recognized that HCP would provide continued protection to the flycatcher habitat,” Wolfe said. He added there are already more flycatcher pairs in the Valley than the habitat recovery plan calls for. He said 56 flycatcher territories were estimated in this area, and the FWS goal was 50, so he did not see the need for additional critical habitat designation.

Murphy said the goal of designating critical habitat for endangered species like the Southwestern willow flycatcher is to ensure their survival and recovery. He said an area that might not contain the species might be designated because of its connectivity to other habitats along the river corridor. The flycatcher habitat is unique, he said, in that this the only bird that nests in shrubs and trees with branches that are vertically oriented like the willows and saltcedar (tamarisk.)

Texas Commissioner Pat Gordon asked Murphy about the nine miles of critical habitat near Elephant Butte that was designated in January. Murphy said the Elephant Butte habitat “is not only significant to the Rio Grande Basin, it’s significant to the population as a whole. What we look at is an area that is essential to the survival of the species knowing that periodic inundation will occur and we feel that is probably beneficial to flycatcher habitat over the long run, but we could not ignore the fact that there are a significant number of territories there with high productivity levels.”

Murphy said when he moved to New Mexico in 1999 Elephant Butte Reservoir was nearly full, and it stayed that way for quite awhile. When the water levels receded in the reservoir, habitat appeared for the flycatchers, which took advantage of it and experienced a rebounding in their population as a result…

Water commissioners have reason to be concerned over endangered species’ effect on water administration, given the ongoing challenge to keep enough water in New Mexico’s rivers to sustain the Rio Grande Silvery minnows, another endangered species. “The Rio Grande Silvery minnows are at an all-time low,” Murphy reported to the Rio Grande Compact Commission. Last year 51 miles of the main channel of the Middle Rio Grande dried up, so the FWS undertook a salvage operation in which more than 4,200 silvery minnows were salvaged and relocated.

More endangered/threatened species coverage here and here.


The price tag for Sterling’s deep injection wells for RO brine escalates from $80,000 to $2.3 million

March 29, 2013

reverseosmosiswaterplantschematic

From the Sterling Journal-Advocate (David Martinez):

[Sterling Public Works Director Jim Allen] told the council that Public Works was working on a number of water and sewage issues around the city – most of them directly or indirectly related to construction of the new water treatment plant.

The one that stands out: Deep injection wells used to pump the treated wastewater from the reverse osmosis filtration, estimated to cost $80,000 at the start of the project, will now cost about $2.3 million, according to a March 10 estimate. About $1.3 million of that cost would go toward the construction of one of the two pumps, which is located above the railroad tracks north of the plant…

The wells themselves, buried about 7,000 feet underground, have already been constructed. They were included in one of three bid packages for the project – the other two being a pipeline project and the water treatment plant itself, which is in the final construction stages.

Allen told the council the increased cost comes from the pumping equipment needed, as well as some stainless steel piping needed for the aboveground operation. The pipes might need to handle 2,200 to 2,600 pounds of pressure per square inch, which Allen said is a “monumental number.”[...]

Allen told the Journal-Advocate the $2.4 million also isn’t set in stone; he, Kiolbasa and others will be working with the estimates for a more solid cost…

In related projects concerning the plant, Public Works is continuing to redrill and rehabilitate the city’s raw water wells. The effort is part of a plan to have enough raw water to actually put through to the water treatment plant.

In February the council heard that the plant planned on having the ability to pump more than 7,900 gallons of water per minute, but that it could only pump about 5,500 gallons at that point because of degraded wells.

More infrastructure coverage here.


CSU to offer low-cost irrigation efficiency audits for farmers #codrought

March 28, 2013

irrigatedagriculture

From the Loveland Reporter-Herald:

A grant from the U.S. Department of Agriculture to CSU’s Center for Agricultural Energy will pay for reduced-cost irrigation efficiency audits for growers with center pivot systems. Center pivot irrigation is common on Colorado’s Front Range and Eastern Plains. Water is pumped onto fields by impact sprinklers mounted on overhead pipes that roll in sweeping arcs across farmland.

For $250, a fourth of the usual $1,000 cost, university technicians will conduct up to three pumping plant audits to gauge efficiency of farmers’ systems, recommend changes and estimate potential savings.

Information and a brief application can be found at www.ext.colostate.edu/cae/audits.html, or by calling Cary Weiner at 970-491-3784.

More conservation coverage here.


Colorado-Big Thompson Project update: Carter Reservoir 80% full

March 28, 2013

coloradobigthompsonprojecteastslopesystemncwcd

From email from Reclamation (Kara Lamb):

Just a quick e-mail to let you all know that the routine work we were doing down around Flatiron has completed. As a result, Pinewood water levels are on their way back up to more typical elevations for this time of year. Flatiron Reservoir water levels will start to come back up–and begin fluctuating again, as is normal. And, the pump to Carter Lake will go back on before the end of the day Thursday, March 28. As of this afternoon, Carter Lake is 80% full.

More Colorado-Big Thompson Project coverage here.


Reclamation Releases a Final Supplemental Environmental Assessment and Finding of No Significant Impact on Ridgway Dam Hydropower Interconnection Facilities

March 28, 2013

ridgwayreservoir

Here’s the release from the Bureau of Reclamation (Steve McCall/Justyn Hock):

Reclamation announced today that it released a final Supplemental Environmental Assessment and Finding of No Significant Impact on Ridgway Dam Hydropower Interconnection Facilities. The supplemental EA and FONSI augments the 2012 Ridgway Hydropower EA and FONSI and addresses additional details and information on the interconnection and transmission facilities.

Reclamation will issue a license agreement to Tri-State Generation and Transmission Association for construction of interconnection facilities to interconnect Tri-County Water Conservancy District Hydropower facilities to the existing 115-kV transmission line that runs along U.S. Highway 550. In addition, a memorandum of agreement will be signed with Tri-County to relocate dry storage facilities and utilities operated by Colorado Parks and Wildlife as part of Ridgway State Park.

Tri-County is currently constructing the hydropower facilities at Ridgway Dam on the Uncompahgre River in Ouray County, Colo. and operates and maintains Ridgway Dam.

The final EA and FONSI are available on our website under the “environmental documents” heading [or] by contacting Steve McCall with Reclamation in Grand Junction at (970) 248-0638.

More hydroelectric coverage here and here.


Fountain Creek: ‘Colorado Springs has taken its job very seriously’ — Steve Gunderson

March 26, 2013

fountaincreekthrucoloradospringsfromdippity

From The Colorado Springs Gazette (Barbara Cotter) via The Denver Post:

Nearly 10 years, $450,000 in penalties and $170 million in fixes later, Colorado Springs Utilities is done with a compliance plan the state imposed over series of wastewater spills into Fountain Creek and some of the tributaries that feed it.

“I would say this has been quite a success story, and Colorado Springs has taken its job very seriously,” said Steve Gunderson, director of the Water Quality Control Division of the state Department of Public Health and Environment. “Why we decided to take enforcement action almost 10 years ago is that we were seeing a pattern of problems. Really, it’s amazing how that pattern has largely disappeared.”[...]

Earlier this month, the Water Quality Control Division sent a letter to Utilities officials notifying them that it was closing the books on the order because all requirements had been met.

More Fountain Creek coverage here and here.


Northern Water’s Spring Water Users Meeting will be held Thursday, April 11 #codrought

March 24, 2013

coloradobigthompsonprojecteastslopesystemncwcd

From email from the Northern Colorado Water Conservancy District:

Northern Water’s Spring Water Users Meeting will be held Thursday, April 11 at the Thomas M. McKee Building at The Ranch, Loveland, CO. starting at 8 a.m.

The Spring Water Users Meeting is a forum to discuss the current water situation and water-related issues. The 2013 meeting will include updates on the current water year, the Northern Integrated Supply Project and the Windy Gap Firming Project. Go to the
April Calendar page for more information and to register online. Business group registration is now available. The last day to register online is April 9.

Spring Water Users Meeting Agenda

More Colorado-Big Thompson Project coverage here and here.