Fryingpan-Arkansas Project update: “We can’t dry up the creeks” — Kara Lamb #ColoradoRiver

September 1, 2014
Fryingpan-Arkansas Project via the Southeastern Colorado Water Conservancy District

Fryingpan-Arkansas Project via the Southeastern Colorado Water Conservancy District

From The Aspen Times (Scott Condon):

The Fryingpan-Arkansas Project diverted about 80,200 acre-feet of water under the Continental Divide to the Front Range this year, according to Kara Lamb, spokeswoman for the U.S. Bureau of Reclamation, which operates the system.

That is about 67 percent higher than the average diversion of 48,000 acre-feet over the 52-year lifetime of the system, she said. More water was diverted this year because of a higher-than-average snowpack and lots of rain starting in mid-July, according to Lamb.

Nevertheless, river and stream water levels have dropped to the point where diversions must be stopped to maintain minimum stream flows.

“This week and next week, we are shutting down the diversion system,” she said Friday. “We can’t dry up the creeks.”

Ruedi Reservoir is about 93 percent full right now. That’s slightly above average, according to the Reclamation Bureau’s records. The amount of water currently being released from Ruedi Dam is 267 cubic feet per second, about average for Sept. 1.

Water is still being diverted from the headwaters of the Roaring Fork River east of Aspen. The Independence Pass Transmountain Diversion System has diverted an estimated 59,400 acre-feet thus far this water year, which started in October 2013, according to water data on the Colorado Division of Water Resources website. Kevin Lusk, a water-supply engineer with Colorado Springs Utilities helped The Aspen Times interpret the data on the state’s website.

The average annual diversion over the past 79 years has been 42,000 acre-feet. This year’s diversion is already 17,400 acre-feet above average, or 41 percent higher.

The diversion system operated by the Twin Lakes Reservoir and Canal Co. taps a 45-square-mile area at the headwaters of the Roaring Fork River. The system diverts water from the Roaring Fork River near Lost Man Campground. In addition, it diverts some of the water in Lost Man Creek, Lincoln Creek, Brooklyn Creek, Tabor Creek, New York Creek and Grizzly Creek, according to a description on the website of Roaring Fork Conservancy, a Basalt-based nonprofit that monitors water quantity and quality issues.

The conservancy’s weekly watershed river report, released each Thursday, showed that Twin Lakes Tunnel was diverting water at a rate of 80 cubic feet per second on Aug. 28 from the Roaring Fork River headwaters. Meanwhile, the river was flowing at only 49 cfs in Aspen that same day.

The Roaring Fork River is dammed near Lost Man Campground. The river below the dam runs at a trickle. It’s replenished to some degree by various creeks before it reaches Aspen.

Without the diversion, the Roaring Fork River flow would be 129 cubic feet per second in Aspen, or about 2.5 times what it is running now. Superior water rights allow the Twin Lakes Reservoir and Canal Co. to divert an amount greater than the river flow.

More Fryingpan-Arkansas Project coverage here.


There are 44 transbasin diversions in Colorado that move water between river basins. Tour some with CFWE! #ColoradoRiver

August 26, 2014

USBR finds $2 million for the Arkansas Valley Conduit for the current fiscal year

August 15, 2014

Arkansas Valley Conduit Comanche North route via Reclamation

Arkansas Valley Conduit Comanche North route via Reclamation


From The Pueblo Chieftain (Chris Woodka):

The Arkansas Valley Conduit has received $2 million for the current fiscal year through reprogramming of funds within the Bureau of Reclamation, according to Colorado Democratic U.S. Sens. Michael Bennet and Mark Udall.

“Folks in Southeast Colorado have been waiting a long time for the federal government to fulfill its promise to build the Arkansas Valley Conduit,” Bennet said. “Making these resources available for the conduit is crucial to completing this phase of the project and moving it one step closer to completion.”

Earlier this year, the senators backed legislation that loosened purse strings within the Bureau of Reclamation and allowed for transfer of funds to projects such as the conduit, which was first authorized in the 1962 Fryingpan-Arkansas Act.

The Southeastern Colorado Water Conservancy District, sponsor of the project, was dismayed when President Barack Obama’s budget submitted to Congress contained only $500,000 in funding this year. More was needed to complete planning and feasibility analysis before the design work and land acquisition can begin.

“Southern Coloradans have been counting on the Arkansas Valley Conduit’s construction for access to clean drinking water — they’ve been waiting long enough,” Udall said.

U.S. Reps. Scott Tipton and Cory Gardner, both Colorado Republicans, also support the conduit and applauded the news.

“This completion of the Arkansas Valley Conduit will ensure the continued delivery of clean drinking water to families, agriculture producers and municipalities throughout Southeastern Colorado,” Tipton said.

The $400 million conduit is in its early stages, having gained approval last year from Reclamation for the 120-mile route from Pueblo Dam to Lamar and Eads.

It would serve 50,000 people in 40 communities by providing filtered drinking water. Most of the communities along the route rely on wells and many of them are facing water quality compliance issues that could force more expensive alternatives to the conduit.

“The support we have gotten from Congress, Gov. John Hickenlooper and James Eklund of the Colorado Water Conservation Board has been tremendous,” said Jim Broderick, executive director of the Southeastern district. “This will allow us to move the project forward as was intended more than 50 years ago.”

Hickenlooper praised the decision: “We have worked closely with all parties to stress the need for this conduit and will continue to support Southeastern and local government in the hard work to bring this project to fruition.”

From Governor Hickenlooper’s office:

Gov. John Hickenlooper today released the following statement on the Bureau of Reclamation’s decision to redirect $2 million to fund the Arkansas Valley Conduit.

“The Arkansas Valley Conduit will serve 50,000 people in more than 40 communities in southeastern Colorado. We commend the Bureau of Reclamation for prioritizing this project and thank the leadership of the Department of the Interior, Southeastern Colorado Water Conservancy District, as well our congressional delegation for ongoing efforts to deliver funding for this critical project. We have worked closely with all parties to stress the need for this conduit and will continue to support southeastern and local government in the hard work to bring this project to fruition,” Hickenlooper said.

The conduit, a water pipeline originally envisioned as part of the federal Fry-Ark Project legislation in 1962, will assist communities experiencing high water treatment costs by providing water from Pueblo Reservoir. The latest funding will assist with preconstruction costs associated with the 130-mile project.

More Arkansas Valley Conduit coverage here and here.


Southern Delivery System: Pueblo county firms net $65 million in orders during construction

August 7, 2014
Southern Delivery System route map -- Graphic / Reclamation

Southern Delivery System route map — Graphic / Reclamation

From The Pueblo Chieftain (Chris Woodka):

The estimated construction cost of the Southern Delivery System, a water pipeline from Pueblo Dam to Colorado Springs, has been lowered to $841 million, about $145 million less than earlier estimates.

“It’s our responsibility to manage project costs as closely as possible to protect the investment being made by the SDS partner communities,” said Janet Rummel, spokeswoman for Colorado Springs Utilities.

The timing of SDS construction saved money primarily because of lower interest rates and lower pricing for materials and services, she said.

“Competitive bidding has allowed more than 100 Pueblo County-based businesses to benefit from $65 million in SDS spending so far,” Rummel said.

Although most of the benefit from SDS goes to Colorado Springs, Pueblo West, Security and Fountain also are SDS partners.

The pipeline has a capacity of 96 million gallons per day, with 78 mgd going to El Paso County.

Pueblo West will increase its capacity by 18 mgd through a connection to the newly constructed north outlet works.

Its current connection at the south outlet delivers 12 mgd — just above the metro district’s peak-day delivery. The outlet is shared by the Pueblo Board of Water Works and the Fountain Valley Authority. It also will be the hookup for the Arkansas Valley Conduit.

Pueblo West has paid $6.5 million for construction of its SDS connection, and estimates it will have paid a net price of $6.7 million — when all bills and refunds are totaled — by 2017.

The money came from reserves, said Jack Johnston, metro district manager.

“We have cash-funded the project out of reserves that were collected primarily during the growth years,” Johnston said. “They were fees that were set aside to help build the reserves to do capital projects.”

Pueblo West got some of the SDS savings, but just for the construction nearest the dam, where its 36-inch-diameter connection splits off from the 66-inch-diameter line that runs 50 miles north.

“Whatever savings were realized in building the north outlet works were passed on to us,” Johnston said.

Pueblo West had been negotiating an agreement to turn on SDS ahead of schedule, since its spur from the dam will be ready for use ahead of the rest of the project.

However, the board last month delayed action on a draft agreement that could allow early turn-on of SDS. If no agreement is reached, the startup would be whenever Colorado Springs gets the go-ahead from Pueblo County to turn on SDS, expected in 2016.

Colorado Springs must meet Pueblo County’s 1041 permit conditions in order to start SDS.

Those conditions include $50 million in payments, plus interest, to the Fountain Creek Watershed Flood Control and Greenway District; $15 million for road rehabilitation in Pueblo West; and $2.2 million for Fountain Creek dredging in Pueblo. All of those payments are included in the $841 million construction cost.

Colorado Springs also will pay $75 million for wastewater system improvements by 2024 within the city under the 1041 permit, but that cost is not included in the estimate.

More Southern Delivery System coverage here.


“I have been proud to work for years to ensure the [support for] the Arkansas Valley Conduit” — Sen. Mark Udall

July 25, 2014
Arkansas Valley Conduit Comanche North route via Reclamation

Arkansas Valley Conduit Comanche North route via Reclamation

From The Pueblo Chieftain (Chris Woodka):

A draft federal energy and water funding bill includes an additional $90 million for projects such as the Arkansas Valley Conduit, U.S. Sens. Michael Bennet and Mark Udall, both Democrats, said Thursday. The Senate appropriations committee approved the bill, which contains a provision supported by both senators that explicitly makes data collection and design work eligible for funding through these accounts. It will help ensure the Arkansas Valley Conduit is eligible for these funds and sends a clear signal to the Bureau of Reclamation that the conduit is a priority project.

The board of the Southeastern Colorado Water Conservancy District, conduit sponsor, was dismayed earlier this year when it learned only $500,000 was budgeted for the conduit next year. It is hoping to get at least $3 million for continuing data and design tasks that will lead to construction of the $400 million conduit.

The conduit is the final piece of the Fryingpan-Arkansas Project, authorized in 1962. When complete, the 130-mile pipeline will provide clean drinking water to 50,000 people in 40 communities east of Pueblo.

“For more than five decades, folks in Southeastern Colorado have been waiting for the federal government to fulfill its promise to build the Arkansas Valley Conduit.

That’s far too long for these communities to wait for a reliable source of clean drinking water,” Bennet said.

“I have been proud to work for years to ensure the federal government supports the Arkansas Valley Conduit. This funding brings the people of Southeastern Colorado one step closer to having a clean, safe and reliable source of water,” Udall said.

More Arkansas Valley Conduit funding here and here.


SDS construction reaches Colorado Springs ahead of schedule and under budget — The Colorado Springs Gazette

July 24, 2014
Southern Delivery System route map -- Graphic / Reclamation

Southern Delivery System route map — Graphic / Reclamation

From The Colorado Springs Gazette (Emily Donovan):

Huge pipes being tunneled underground near the intersection of Powers Boulevard and Constitution Avenue is the first big sign after almost two decades of work to increase the water available to the Colorado Springs area by a third…

Pipeline construction at the busy intersection is ahead of schedule, expected to be complete in September rather than November, said SDS spokesperson Janet Rummel…

A $125 million facility that will be able to process 50 million gallons of water a day, the treatment plant on the east side of Colorado Springs is halfway constructed, also ahead of schedule. Construction began in March 2013 and will be finished in fall of 2015. The plant is expected to put out drinking water in April 2016…

SDS construction is estimated to cost $847 million – $147 million less than the original estimation in 2009.

Rummel said money was saved by asking engineers to make designs that would be cost-effective without damaging drinking water quality, like keeping every part of the water treatment plant under the same roof instead of separate buildings.

This means SDS will cause less of a utilities rate increase for CSU customers than originally expected in 2009…

“This is the future of Colorado Springs,” said Jay Hardison, CSU water treatment plant project manager.

More Southern Delivery System coverage here and here.


Water Lines: Colorado needs a better water plan — Jim Pokrandt #ColoradoRiver #COWaterPlan

July 16, 2014


From the Glenwood Springs Post Independent (Jim Pokrandt):

It’s almost time for football training camps, so here’s a gridiron analogy for Colorado River water policy watchers: Western Colorado is defending two end zones. One is the Colorado River. The other is agriculture. The West Slope team has to make a big defensive play. If water planning errs on the side of overdeveloping the Colorado River, the river loses, the West Slope economy loses and West Slope agriculture could be on the way out.

This is how the Colorado River Basin Roundtable is viewing its contribution to the Colorado Water Plan ordered up by Gov. John Hickenlooper. A draft plan will be submitted this December and a final plan in December 2015. The Roundtable is assessing local water supply needs and environmental concerns for inclusion into the plan and there is plenty of work to consider in the region. But the big play may very well be the keeping of powerful forces from scoring on our two goal lines.

Here’s why: Colorado’s population is slated to double by 2050. Most of it will be on the Front Range, but our region is growing too. Mother Nature is not making any new water. We still depend on the same hydrological cycle that goes back to Day 1. So where is the “new” water going to come from? Right now, there seems to be two top targets, the Colorado River and agriculture (where 85 percent of state water use lies in irrigated fields). Colorado needs a better plan.

The Colorado Basin Roundtable represents Mesa, Garfield, Summit, Eagle, Grand and Pitkin counties. This region already sends between 450,000 and 600,000 acre feet of water annually across the Continental Divide through transmountain diversions (TMDs) to support the Front Range and the Arkansas River Basin.

That water is 100 percent gone. There are no return flows, such as there are with West Slope water users. On top of that, this region could see another 140,000 acre feet go east. A number of Roundtable constituents have long-standing or prospective agreements with Front Range interests wrapped around smaller TMDs. Existing infrastructure can still take some more water. That’s the scorecard right now. We assert another big TMD threatens streamflows and thus the recreational and agricultural economies that define Western Colorado, not to mention the environment.

In the bigger picture, the Colorado River Compact of 1922 requires Colorado to bypass about 70 percent of the river system to the state line to comply with legal limits on depletions so six other states can have their legal share of the water. Failure to do so, by overdeveloping the river, threatens compact curtailments and chaos nobody wants to see. For one thing, that kind of bad water planning could result in a rush to buy or condemn West Slope agricultural water rights.

The Roundtable has heard these concerns loudly and clearly from its own members across the six counties as well as from citizens who have given voice to our section of the water plan, known as the Basin Implementation Plan (BIP). A draft of the BIP can be viewed and comments offered by going online to http://coloradobip.sgm‐inc.com/. It is under the “Resources” tab.

Jim Pokrandt is Colorado Basin Roundtable Chair.

More Colorado Water Plan coverage here.


Follow

Get every new post delivered to your Inbox.

Join 996 other followers

%d bloggers like this: