Gypsum: LEDE Reservoir enlargement costs are up to just over $5 million

ledereservoirgypsum.jpg

From the Eagle Valley Enterprise (Derek Franz):

LEDE has a current capacity of 473 acre feet of water. The latest plans are to expand it to 947 acre feet. The expansion will submerge some small wetland areas that are around the reservoir at its present size and the town has plans to compensate for that loss by replacing the wetland areas with new ones. Those plans are mainly what need approval from the Corps of Engineers and it’s unclear if that will happen.

“We might want to get some other plans in the works if it looks like they’re going to fight us on these,” said water attorney Ramsey Kropf. “Then again, they might fight us on anything we propose.”

Costs were also bumped up in 2010 when the latest plans for the expansion were approved by Gypsum Town Council. Council members opted to expand the reservoir to 947 acre feet instead of 680 acre feet as originally planned. That budget presented the town with a $680,000 funding shortfall. However, the larger option was a much better value per acre foot.

At that point, the project was estimated to cost about $4.5 million. Now that number is just over $5 million, leaving a difference of $536,000 to scratch up.

More infrastructure coverage here.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.

Join 521 other followers

%d bloggers like this: